Natural Disaster Relief and Recovery Arrangements (NDRRA) - CA Project 1Website/Report(not documented) 
Project leadPartnershipsCondamine Alliance (part of Southern Queensland Lanscapes) 
IndustriesOther 
ActivitiesOn-ground work 
Case study type(none) 
Funding sourceNDRRA - joint Commonwealth and State 
Funding amount$7,260 
In-kind contribution(not documented) 
Start date1 July 2017 
End dateJune 2019 
SummaryMechanical excavation by floating excavator to remove silt and nuisance vegetation and stabilise bed and banks to improve water quality and protect community assets. 
Benefits
In total, 88 projects were completed by 30 June 2019. These included:
 
 Approximately 290,000 tonnes of sediment have been prevented from polluting the coastline every year; including the Great Barrier Reef and Moreton Bay environments. Natural Disaster Relief and Recover Arrangements Summary Report Lesson(not documented) 
Reference ID(none) 
Last updated: 18 March 2021 This page should be cited as: Department of Environment, Science and Innovation, Queensland (2021) Natural Disaster Relief and Recovery Arrangements (NDRRA) - CA Project 1, WetlandInfo website, accessed 8 May 2025. Available at: https://wetlandinfo.des.qld.gov.au/wetlands/resources/tools/wetland-project/natural-disaster-relief-and-recovery-arrangements-ndrra-ca-project-1-8ed2/  | 


 